Skip to main content

Increased Capacity for Manufacturing Hydac Technology Industrial Pavilion

About

  • Lead Partner

    Charles Webster

  • Client

    Hydac Technology Ltd

  • Location

    Witney

  • Value

    £3,000,000

  • Dates

    Completed February 2019

New industrial pavilion, to provide for the expansion of Hydac Technology’s manufacturing plant, with sharp detailing, all set within mature landscape in an active business park.

Steel frame structure with built-up insulated metal roof and wall claddings, offices on first floor mezzanine and ancillary provisions on the ground floor, 2No chargers for electric cars, connectivity of IT. services with the sister building on the business park.

Pre-formed mitred corners to front elevation, galvanised PFC perimeter detail to ground floor slab and concrete beam. 200sqm of open plan offices fitted to Category B with an additional 220sqm of open plan offices fitted to Category A for later client adoption. The full extent of the ground floor concrete slab is designed to 50KN/m2 and is 200mm thick to prevent vibration, allowing full flexibility for placing machinery and racking/shelving systems as well as fork lift truck manoeuvering, with dedicated pedestrian walkways.

Due to manufacturing equipment demands, a new 12 Kva substation installation was commissioned and coordinated via SSE.

Project Team

For enquiries relating to this project, please contact our project team leads